New mold trial (T1) checklist: before mounting, on the machine, and afterward

A practical checklist, from preparation to reporting, that reduces time and material loss during a mold trial.

October 16, 2026 · 2 min read

The first trial (T1) is often the most expensive hour: the machine, operator, toolmaker and material all wait together. Preparation shortens this significantly.

1. Before mounting the mold

  • Machine compatibility: Mold dimensions, tie-bar spacing, closed height, opening stroke, locating ring and nozzle radius.
  • Tonnage and shot size: Is the required clamping force below the machine's capacity? Is the shot volume in a suitable range? (Clamping force calculation)
  • Water circuits: Number of circuits, connection order, inlet/outlet markings, leaks. Pressure-test with water and visually confirm each circuit flows.
  • Hot runner: Check heaters, thermocouples and cabling; heating up must be done in stages, and allow time for moisture to clear.
  • Mold cleaning and lubrication: Remove rust-preventive oil, lubricate sliding surfaces.
  • Raw material: Correct grade, drying complete, suitable dew point.

2. First steps on the machine

  1. Set mold protection values to high safety (low speed, low force).
  2. Open/close slowly at first; visually confirm no moving parts collide.
  3. Set the hot runner and mold temperature and wait long enough.
  4. Start with short shots (50%-75%-90%) and observe the fill balance; don't apply holding pressure on the very first shot.
  5. Once filling is complete, set up the V/P changeover, then holding and cooling.

3. What to record

  • Machine and screw diameter, nozzle, dosage, cushion, V/P changeover, speed profile, pressure limit.
  • Melt temperature (measured with a probe), mold surface temperature, water temperature and flow rate.
  • Fill time, holding, cooling, total cycle, part weight.
  • Photos: The short-shot series and any defects.

4. After the trial

  • Measurement report (critical dimensions, warpage, shrinkage).
  • Defect list: location, type, probable cause; as a clear work order for the toolmaker.
  • Mold cleaning, protective oil, storage.
  • Print out the process sheet (set sheet) and add it to the mold's file. This is the starting point for the next production run.

Common mistakes

  • Running the hot runner without waiting long enough (splattering if moisture is present).
  • Trying full fill and holding in one go on the first trial, straining the mold and material.
  • Making adjustments one after another without writing down what was changed.
Note: The list in this article is a general template. Combine it with the mold maker's instructions for your mold's specific requirements (hydraulic cores, valve gates, sliding parts).