How to calculate the cost of an injection molded part: unit price item by item
Material, runner and scrap, machine hour, labor, mold amortization and margin. Calculating the unit cost of an injection molded part step by step, with a worked example.

The most common mistake when quoting an injection molded part is to look only at the material. "A 25 g PP part, the resin costs this much per kilo, so the part costs this much" usually leaves out the machine hour, the runner, the scrap and the mold. The result is either a job that loses money or an order that goes to someone else.
The unit cost has five items. Calculating each separately and then adding them up gives you a correct price and shows which item is expensive.
1. Material (including runner and scrap)
The material that goes into the mold in one shot is the parts plus the runner:
Shot weight = number of cavities × part weight + runner weight
If the cold runner is not recovered (not ground and reused), the whole runner is part of the cost. If it goes back in as regrind, only the part that is not returned is counted. With a hot runner mold this item is close to zero. For regrind ratios and their effect on quality, see recycling and regrind management.
Scrap is added to the material as well: with 3% scrap, 97 out of every 100 parts can be sold, so the material per good part increases by a factor of 1/0.97.
Material per part = (shot weight / cavities) × price per kg / (1 − scrap rate)
2. Machine
The machine hourly rate includes the machine's depreciation, energy, maintenance, floor space and the share of overheads allocated to the machine. It has to come from the company's own accounts; it rises with clamp tonnage.
Good parts per hour:
Parts/hour = (3600 / cycle time) × cavities × efficiency × (1 − scrap rate)
Efficiency here is the share of time the machine actually spends producing, after mold changes, breakdowns, waiting for material and stoppages. Using 100% makes the price look lower than it is; 80–90% is a realistic starting point.
Machine cost per part = machine hourly rate / parts per hour
Most of the cycle is cooling, and using a calculated value instead of a guess is the step that improves the quote the most. You can calculate cooling and cycle time with the process analysis. For why wall thickness matters so much, see why cooling time grows with the square of wall thickness.
3. Labor
One operator does not always run a single machine. If one person runs two machines, 0.5 operator is allocated per machine.
Labor per part = (operators per machine × hourly labor cost) / parts per hour
The hourly labor cost includes gross wages plus employer contributions and benefits. If parts are sorted, deflashed or assembled by hand, add that time separately.
4. Mold amortization
If the mold is not invoiced to the customer separately, its cost is spread over the parts:
Mold cost per part = mold price / total production quantity
The total quantity is the expected production over the order, the contract or the life of the mold. On small orders this item can exceed even the material, which is why for low volumes it is often more transparent to quote the mold separately.
5. Extra operations and margin
Packaging, labels, printing, assembly and transport are added per part. The margin goes on top of the total cost. With deferred payment (for example 60 days), the financing cost of the money tied up should also be in the price; when interest rates are high this item can eat a large part of the margin.
Worked example
The values below only illustrate the calculation; replace them with your own prices.
- PP part, 25 g, 4-cavity cold runner mold, runner 8 g per shot (not recovered)
- Resin 60 TRY/kg, scrap 3%
- Cycle time 20 s, efficiency 85%
- Machine hourly rate 900 TRY, 0.5 operator × 300 TRY/hour
- Mold price 1,500,000 TRY, total 2,000,000 parts
- Packaging 0.10 TRY per part, margin 15%
Material: shot 4 × 25 + 8 = 108 g. Per part 108 / 4 = 27 g; with scrap 27 / 0.97 = 27.84 g. Cost 0.02784 kg × 60 = 1.67 TRY.
Parts/hour: 3600 / 20 = 180 shots × 4 cavities = 720 parts; × 0.85 efficiency × 0.97 = 594 good parts/hour.
Machine: 900 / 594 = 1.52 TRY.
Labor: 0.5 × 300 = 150 TRY/hour; 150 / 594 = 0.25 TRY.
Mold: 1,500,000 / 2,000,000 = 0.75 TRY.
Packaging: 0.10 TRY.
Total cost: 1.67 + 1.52 + 0.25 + 0.75 + 0.10 = 4.29 TRY. With a 15% margin the selling price is 4.93 TRY.
In this example machine and material carry almost equal weight. If the runner could be fully returned as regrind, each shot would need 8 g less virgin material and material per part would drop to 1.55 TRY. Cutting the cycle from 20 s to 18 s brings the machine item down to 1.36 TRY. You only see which improvement pays more when the items are shown separately. For ways to shorten the cycle, see the cycle time reduction checklist.
Common mistakes
- Assuming 100% efficiency. Every plant has mold changes and stoppages; the price must carry them.
- Forgetting the runner. On small parts the runner can weigh more than the part.
- Guessing the cycle time. "A similar part ran at 15 seconds" does not hold for a thick wall or a slowly crystallizing material.
- Spreading the mold over a small quantity. On a 10,000-piece job, mold amortization multiplies the unit price; this needs to be discussed openly with the customer.
- Ignoring payment terms. 60–90 days of credit are part of the cost when interest rates are high.
Do the calculation yourself
You can enter all these items on the part cost calculator and see the unit price immediately; currency and payment terms/financing are included. To start from the example part: 25 g, 20 s, 4 cavities. The result is a preliminary estimate; for a firm price, use your own machine hourly rate and the cycle time measured on a trial run.